10 Nov Progress at Blythburgh Coal Shed (3)
Work continues. The siding was infilled with earth, two panels of track laid in and outside of the shed and crumbled brick was barrowed in from a 3 ton pile and laid in between the rails inside and outside of the shed. More repairs were carried out to the fabric of the shed, Danny completed the pointing of the brickwork upon which the shed sits and a gate was erected.