10 Nov Progress at Blythburgh Coal Shed (4)
Work continues. The fencing was completed and the shed floor, a Southwold Railway buffer stop was erected in the shed and the floor was levelled...
Work continues. The fencing was completed and the shed floor, a Southwold Railway buffer stop was erected in the shed and the floor was levelled...










Work continues. The siding was infilled with earth, two panels of track laid in and outside of the shed and crumbled brick was barrowed in from a 3 ton pile and laid in between the rails inside and outside of the shed. More repairs were carried out to the fabric of the shed, Danny completed the pointing of the brickwork upon which the shed sits and a gate was erected.
Work continues and we have laid a siding next to the shed in exactly the same position as it was in the days of the...
Work continues at the shed. Danny is pointing the brickwork and we are fencing off the site. Here too are a couple of photos along...